Home · Articles on balancing and vibration
Maintenance Programs

How to build vibration monitoring and balancing into your maintenance program

As long as vibration only gets measured on a call of 'something's making a noise,' you're always dealing with consequences, not causes. You need the same instrument, the same hands, the same callout time. The only difference is whether the measurements are built into the maintenance schedule or not. Below, we break down how to turn one-off callouts into a program: which machines to include, how often to measure, what to record, when balancing gets scheduled in advance, and who does all of it.

Updated 27 August 2026 · by AXILINE · Vila Nova de Gaia

In short: Build vibration monitoring into maintenance with three moves. First, sort machines by the consequences of failure and give each group its own measurement interval instead of one interval for the whole fleet. Second, set a baseline level and three thresholds for each point, and next to each threshold define the required action, the deadline, and who is responsible. Third, schedule balancing in advance for jobs that predictably cause unbalance: rotor repair, blade or hammer replacement, motor rewinding, installing or relocating the unit, and impeller cleaning.

Three maintenance approaches, and where vibration monitoring pays off most

A typical call sounds like this: the induced-draft fan started making noise this morning, by noon the bearing housing was hot, please come today. By the time the engineer reaches the site, they're no longer dealing with unbalance but with its consequences: a wrecked bearing, stretched studs, sometimes a crack in a weld on the frame. Balancing is still possible in this situation, but it has become the third item after repairs, not the first.

The reason isn't the people or the instrument. It's that the machine has no history. Nobody knows what vibration level this fan had six months ago, so the very first measurement has to be interpreted blind. History only comes from a program.

Run-to-failure

Repair what breaks. On paper it's the cheapest option: you don't pay for measurements and you run components to the end of their life. You pay for it in downtime at the worst moment, rush parts delivery, and damage to neighboring components. The approach genuinely works where the machine is duplicated, cheap, and its shutdown doesn't stop anything else: an extractor fan in a site cabin, one of four identical make-up pumps.

Time-based (by running hours)

Strip down and replace components after a set number of hours or months, regardless of condition. Sudden failures become rarer. In exchange, you throw away perfectly good bearings, and a defect that appears a week after scheduled maintenance sits there quietly until the next one. And every teardown introduces its own new unbalance and new shaft misalignment.

Condition-based

Measure vibration along a route, watch the trend, and step in when the data shows a developing defect. Components are used to their full service life, and work lands inside a planned window. In exchange, you need marked-out measurement points, discipline in keeping to the rounds, and someone who knows how to use the instrument.

One thing is worth remembering about unbalance. The calculated bearing life under ISO 281 is tied to the load acting on it, and an unbalanced mass adds a constant rotating force on top of the working load. This force never switches off for a single minute of operation, and it grows with the square of the speed.

Sources: ISO 281:2007

Which machines to include in the program, and by what criterion

The temptation is understandable: put everything that rotates on the program. A list of two hundred items turns, by the third month, into a signature in the log with no actual measurement behind it, because the route technician physically can't keep up. Select machines deliberately, by a criterion you can explain to the chief engineer.

There's one main criterion: what happens when this machine stops without warning. Everything else just refines the answer.

Review group membership once a year. The fleet changes, regimes change, and a group C machine can become the only one in the chain after a change to the production layout. A program that hasn't been reviewed in three years no longer describes your plant. We covered how to mark out points, capture a baseline level, and track a trend in a separate article on vibration monitoring and routes.

Measurement interval: base it on how fast the defect develops

The calendar is secondary here. The measurement interval has to be shorter than the time your typical defect takes to go from the first noticeable sign to failure. Working rule: the interval should be no more than half that time. Otherwise you'll see the defect exactly once, and it will already be in its final stage.

Benchmarks for typical defects explain why a month turns out to be a sensible unit for most machines.

Measurement intervals only make sense under consistent measurement conditions. The same induced-draft fan gives different numbers at different damper positions. Write the operating regime for the measurement into the program, and require the route technician to wait for it or log the deviation.

Four documents the program rests on

A program doesn't live in the mechanic's head or in an email thread. It needs four documents, and all four are simple. Their absence always shows up at the same moment: when the person who remembered everything goes on leave or changes jobs.

Measurement point map

One page per machine: a diagram of the unit, numbered points on the bearing housings, a direction for each one (horizontal-radial, vertical-radial, axial), the sensor mounting method, the location of the reflective tape for the laser tachometer, and the operating regime for the measurement. After that, the map doesn't change. Measuring at a different point or in a different direction creates a false shift in the trend, and catching the substitution after the fact is almost impossible.

Measurement log or database

One line per measurement, accessible to more than one person. A spreadsheet in a shared folder works; a notebook in someone's pocket doesn't. The database's value shows up in year three, when you can point to a line of thirty measurements and back a decision with numbers instead of opinion.

Baseline levels and thresholds

The baseline level is captured on a machine in good condition after a repair and recorded separately from routine measurements, with the date and conditions. Thresholds are calculated from it. Next to each threshold, list the action, the deadline, and who is responsible — otherwise the threshold stays just a number in a table.

Balancing and repair reports

What was done, in which planes, what mass was fitted at what radius and in what position, what residual running-speed component was achieved, what balance quality grade was specified and under which document. A year later, this report will save you trial runs: the saved influence coefficients (the machine's recorded response to a trial weight) let you get away with one run instead of three.

A number without metadata can't be correctly compared against either a threshold or a previous measurement. ISO 13373-1 requires full identification of the measurement conditions for exactly this reason: so the result is reproducible. For contractual acceptance, this isn't a formality — it's the only way to avoid a dispute later.

Sources: ISO 13373-3:2015

When to schedule balancing in advance, without waiting for a measurement

Some jobs cause unbalance not as a maybe, but predictably. You're going to open the machine anyway, take an acceptance measurement anyway, and spend a shutdown anyway. It makes sense to write balancing into the work order right away, so you don't call people out a second time or open the unit twice.

Scheduling balancing in advance doesn't mean balancing blind. The sequence stays the same: an acceptance measurement after reassembly, comparing the running-speed component against the overall vibration, then a decision. This step often reveals that what's needed isn't balancing but shaft alignment or tightening the mounting feet. What goes into the plan is a window and the resources for the work, not a commitment to fit weights. Evaluate acceptance against the applicable part of ISO 20816 in its current edition, and if a balance quality grade is required, separately against ISO 21940-11.

Sources: ISO 20816-1:2016 · ISO 21940-11:2016

How to link the measurement to a decision: three threshold levels

The most common way a program breaks down looks like this: measurements keep happening, numbers keep piling up, and no decisions get made. The route technician wrote down 4.8 mm/s and moved on, because the document doesn't say what to do with that number. A threshold with no defined action doesn't work.

Build three levels. Calculate the first two from the specific point's baseline level; keep the third as an absolute value and check it against the zones in the applicable part of ISO 20816 — the standard divides machine condition into zones from A to D, from normal for a new machine to unacceptable vibration. The baseline level matters more than the absolute table: a machine with a baseline of 0.8 mm/s that now reads 2.2 has already told you about a developing defect, even though it's formally still in zone B.

LevelHow it's setWhat the route technician doesTimeframeWho decides
1. WarningRoughly double the baseline level, but not above the B/C zone boundaryNotes the exceedance, repeats the measurement ahead of schedule, takes a spectrum (the breakdown of vibration by frequency), records overall and 1x separatelyNext round; sooner for group AArea mechanic
2. AlarmRoughly triple the baseline level, or the C/D zone boundary per the applicable part of the standardReports the same day, repeats the measurement at all points on the unit in three directions, checks tightness and heatOne day to diagnose the causeChief mechanic; a vibration specialist is brought in if the picture is unclear
3. ShutdownAn absolute value per the site's regulations and the machine's data sheet, usually beyond the zone D boundaryActs strictly per the site's instructions: shutdown or switch to standby, immediate notificationImmediatelyThe person responsible under the site's regulations, not the route technician's own judgment

Sources: ISO 20816-1:2016

A sample program structure

Below is a typical structure that's convenient to start from. This is an illustrative example, not anyone's actual site: you work out your own groups, points, and thresholds from your own fleet and your own baseline levels. The value of the table is that each row answers five questions at once, and once it's filled in, the program is ready to sign off.

Equipment groupWhat we measureIntervalWhoWhat we do on an exceedance
A. Critical, no standby: induced-draft fans, feed pumps, main line drivesOverall vibration and 1x, speed, spectrum at all points; phase added if levels riseMonthlyIn-house route technician; area mechanic reviews spectraLevel 1: repeat in two weeks. Level 2: diagnose the cause within one day; balance at the nearest window if 1x dominates. Level 3: shutdown per the site's regulations
B. Important, with standby: 2-of-3 pumps, supply-air fans, compressors with standbyOverall vibration and 1x, speedQuarterlyIn-house route technicianLevel 1: unscheduled measurement in a month. Level 2: switch to standby and diagnose at the planned window
C. Other auxiliary and duplicated machinesOverall vibrationEvery six months, or on requestIn-house route technician, or the maintenance team during scheduled serviceDiagnosis at scheduled maintenance; monitoring until then
Fast-wearing working elements: crushers, mulchers, shreddersOverall vibration and 1x; separately, checks on the completeness and mass-matching of hammers and knivesMonthly, and after every change of working elementsIn-house staff; balancing in-house or by a contractorBalancing right after replacing the set; acceptance measurement logged in the report
Events: after rotor repair, motor rewinding, installation, impeller cleaningAcceptance measurement: overall, 1x, spectrum, residual unbalance if neededEvery time on reassembly, regardless of the calendarMaintenance team together with a vibration specialistBalancing in the same work order; a new baseline level is recorded after acceptance

The row people forget most often: who updates the baseline level, and when. Without it, within a year the thresholds stop matching the machine, and the program starts producing either false alarms or silence.

Who does the work: in-house staff, a contractor, or a mixed setup

This isn't a question of principle — it comes down to how often you need the work done and how fast you need a response.

In-house staff with an instrument

Same-day response, familiarity with your own machines, and rounds that don't depend on someone else's schedule. Balancing a fan after cleaning the impeller happens at the next stoppage, not two weeks later. In exchange, you need someone who's been trained and has this route written into their duties. The main risk isn't money: the instrument ends up sitting in a cabinet once the trained person leaves or gets pulled onto emergency work.

A contractor on call

You don't keep the expertise in-house and don't buy an instrument, and you get experience with complex cases right away. In exchange, you pay in waiting for a callout and having to prepare the window and access in advance. A regular route run entirely by a contractor gets expensive, and the route itself still needs your own person to open up platforms and hold the operating regime.

A mixed setup

In-house staff covers the rounds, the trend, and the simple cases: single-plane balancing on a rigid rotor, repeat measurements, trim balancing (a quick follow-up correction) using saved coefficients. A contractor gets brought in for ambiguous cases, overhung and two-plane rotors, resonance, and acceptance after a major overhaul. For most plants, this setup turns out to be the most robust.

Where to start, and what your person needs to know at the first stage

Don't try to launch the program across the whole fleet at once. Take five or ten group A machines and carry the full cycle through on them.

  1. 1

    Select the machines and document the points

    Five or ten units, each with a point map for its bearing housings, with directions and the sensor mounting method. Wherever a housing can't be reached while running, solve the access problem right away.

  2. 2

    Capture the baseline levels

    Best done right after a repair, on a machine in good condition, at an agreed operating regime. Record the conditions. This is your reference point for years ahead.

  3. 3

    Set the thresholds and actions

    Three levels, and next to each one an action, a deadline, and who's responsible. Check the wording for clarity: someone on the night shift will be reading it.

  4. 4

    Add the rounds to the maintenance schedule

    The round needs to be a work order with a date and an assigned person, not a task for 'whenever there's time.' Otherwise it loses out to any emergency job.

  5. 5

    Review after a quarter

    What didn't get done, where the points turned out inconvenient, where a threshold produced false alarms. After that, expand the program to group B.

AXILINE engineers design and manufacture the Balanset instruments and do the balancing themselves on site visits. We provide hands-on training on your own machines and ongoing consulting support afterward, once your staff is running the route independently. A practical way to start looks like this: on the first visit, we balance whatever is getting in the way of running right now, and at the same time mark out the points and capture the baseline levels, so the program rests on your own real numbers instead of a table from the internet. The Balanset-1A fits this setup by design: two accelerometers, a laser phase sensor using reflective tape, a two-channel USB module, and a laptop, with the case kit weighing under five kilograms. The instrument computes single- and two-plane balancing, displays overall vibration and 1x, phase, speed, spectrum, and the time waveform, supports fixed positions and drilling calculations, stores influence coefficients, keeps an archive, and generates reports. For building into a machine tool or test stand, there's a Balanset-1A OEM version without the case.

Sources: Balanset-1A operation manual · Balanset-1A manufacturer specification

Frequently asked questions

How often should we start measuring if vibration has never been measured at the plant before?

Take your five or ten most critical machines and do a round once a month. A month isn't arbitrary: it fits inside half the typical time a rolling-element bearing defect takes to develop, and it lets you catch unbalance from product buildup before it turns into a problem. Bring the rest of the fleet on after a quarter, once you've confirmed the rounds are actually happening.

Is it mandatory to balance the rotor after every repair?

Always plan for balancing, but only carry it out based on the acceptance measurement's result. After reassembly, take the overall vibration and the running-speed component. If 1x dominates and the level is above what's acceptable, fit weights in the same work order. If the overall vibration is much higher than 1x, look at shaft alignment, mounting, or looseness: balancing here would only waste the shutdown.

Can a route be run with a simple vibrometer that has no phase sensor?

For trending the overall level, yes, a simple vibrometer is enough. But the moment a threshold trips, you need a spectrum and a separation of overall vibration from 1x, otherwise the decision gets made by guesswork. And for balancing, a phase sensor is mandatory: without a reference mark, the instrument can't tie the vibration to the rotor's position or calculate a correction.

Who should sign the report, and how long should it be kept?

The report is signed by whoever performed the work and by whoever accepted the result on the operating side. Keep it for as long as the machine is in service, together with the baseline levels and the point map. The archive's value shows up after a year or two: you can see that after the last balancing the level was 1.1 mm/s, and you can tell whether something is trending up or the machine is simply like that.

What do we do if a threshold is exceeded but the machine can't be stopped?

Describe this case in the program in advance, not in the moment it happens. A working approach: increase measurement frequency to once or twice a week, take a spectrum and watch the slope of the trend line, prepare parts and a repair window, and set an absolute threshold at which shutdown happens regardless of production plans. The decision to keep running with elevated vibration is made by the person responsible under the site's regulations, not by the route technician.

How many machines can one person realistically cover on a round in a single shift?

Count by number of points and travel time between them, not by number of machines. Each point takes a few minutes including mounting the sensor and waiting for a stable regime, plus walking time, plus getting a permit and removing guards. Time this on your own site, record it, and only then plan the coverage. A program built around an ideal pace falls apart at the first emergency job.

Related content

Vibration monitoring: route, baseline level, alarm thresholds and trend

Select machines by criticality and cost of downtime, not by ease of access. Mark points at the bearing housings, fix the directions and the sensor mounting method, and stop changing them. Take the baseline level on a sound machine after a repair: that's your reference point. Build alarm thresholds off the baseline in three steps (warning, alarm, shutdown), and use the A–D zones from ISO 20816 as an absolute ceiling. A rising level means 'go investigate,' not 'go balance.'

Open page

Vibration Measurement Units: mm/s, g, µm, and What RMS Means

Vibration is described by three quantities: displacement in µm (usually peak-to-peak), velocity in mm/s (usually RMS — root-mean-square value), and acceleration in m/s² or g. Displacement works at low frequencies and on shafts, velocity gives a universal condition assessment for housings over the 10–1000 Hz band, and acceleration shows up high frequencies, bearings and impacts. Converting between quantities is only possible for a single component at a known frequency, and the 1.41 factor between RMS and peak only holds for a sine wave. That's why a figure with no stated quantity, amplitude type, frequency band and measurement point simply has nothing to be compared against.

Open page

Conveyor Pulley Balancing: Drive, Take-Up, and Bend Pulleys

Yes, we balance conveyor pulleys on site, in their own bearing units, with weights on the end discs in two planes. An honest caveat: below roughly 120 rpm the forces from imbalance are negligible, and the running frequency drops toward the lower measurement limit. So we first check belt tension and tracking, lagging wear, buildup, the motor-gearbox unit, and the bearing units. Balancing is worthwhile on pulleys from ~120 rpm up, after a shell repair, when a factory weight has been lost, or when there's water or buildup inside the body.

Open page

Describe your equipment and the problem

We'll answer your questions, clarify the details, and let you know what's needed for an estimate and a visit.

Submit a Request WhatsApp Pricing